Press releases

12.12.2022

Meeting newsletter of the secretariat of the regional Cooperation Group

calls for applications and deadlines for the new and competent Finland 2021-2027 programme

  • Fixed-term application period for the business development grant (ERDF) from 9 January to 28 February 2023
  • Continuous application of the operating environment development grant and business networked research projects (JTF) at jointly agreed processing dates. As soon as possible in early 2023.
  • Continuous application process for the Business Development Grant (JTF). As soon as possible in early 2023.

Open calls for applications can be found on the website EURA 2021: Call for applications

Opening JTF searches

The Regional Council of Northern Ostrobothnia and the Centre for Economic Development, Transport and the Environment (ELY Centre) have prepared a continuous application period for the JTF for 2023 with application dates of 31 March, 31 August and 30 November. The days are the same for the Regional Council of Northern Ostrobothnia, the ELY's ERDF and ESF-type development projects, as well as the ELY's operating environment support projects (TYT) and business networked research projects. There is a continuous search for business subsidies. The Regional Council of Northern Ostrobothnia has prepared the JTF application process for Northern Finland together with the Regional Council of Lapland and the Regional Council of Kainuu.

Corporate Finance Strategy and Policy (JTF) of the Financing Unit of the Centre for Economic Development, Transport and the Environment of Northern Ostrobothnia

The corporate finance strategy has been drawn up to be used in the evaluation of grant applications and to support decision-making in the region of Northern Ostrobothnia for projects funded by the Just Transition Fund. The publication of the strategy increases the transparency of decision-making and facilitates the work of those planning to apply for a grant. In addition, the strategy will improve coordination between national business support funding and regional development fund and EAFRD business support in Northern Finland. The strategy will be submitted to the provincial cooperation group for approval.

The Secretariat of the regional Cooperation Group supports the following projects to be funded under the Finnish Structural Funds Programme for Leverage from the EU 2014-2020:


Safe and sustainable dark / ERDF
Responsible authority: Regional Assembly of Oulu Region
Applicant: University of Oulu
Total cost estimate 149 800 €
Requested ERDF and state funding 104 860 €

The project seeks an innovative approach to the design and implementation of lighting in urban environments. The aim is to optimise the use of low illuminance levels with design solutions that are researched in terms of their correctness and impact, combined with intelligent light control technology. The goal is an energy-efficient and ecological dark-time urban environment and culture that supports the well-being of people and nature.

Fascinating stories to make Rokua Geopark an attractive area / ERDF
Responsible authority: Regional Assembly of Oulu Region
Applicant: Humanpolis Oy
Sub-applicant: Kajaani University of Applied Sciences
Total cost estimate 215 152 €
Requested ERDF and state funding 150 607 €

In the project, the stories of the Rokua Geopark area are compiled into a story database that brings them to entrepreneurs, associations, schools and other actors in the area in a new way.

Continuously pressed ore stone research crusher / ERDF
Responsible authority: Regional Assembly of Oulu Region
Applicant: University of Oulu
Total cost estimate 361 560 €
Requested ERDF and state funding 253 092 €

The aim of the project is to develop a digital research environment for ore rock crushing based on continuous crushing.

QUALITY - Quality Testing Investment / ERDF
Responsible authority: Regional Assembly of Oulu Region
Applicant: Centria University of Applied Sciences Ltd
Total cost estimate 123 000 €
Requested ERDF and state funding 84 350 €

The most important measure of the project is the development of testing and measuring equipment.

Material research single-chiller X-ray diffractometer / ERDF
Responsible authority: Regional Assembly of Oulu Region
Applicant: University of Oulu
Total cost estimate 550 000 €
Requested ERDF and state funding €385,000

Single-kider X-ray diffractometer (SC-XRD) intended for procurement at the Materials Analysis Centre of the University of Oulu.

Learning environments supporting the green transition - Ecocar/ERDF
Responsible authority: Regional Assembly of Oulu Region
Applicant: Joint municipal authority for education OSAOTotal cost estimate 328 356 €
ERDF and state funding requested 229 849 €

The project develops and strengthens education infrastructure that supports sustainable construction and mobility.

Kuusamo Circular Economy 2030 / ERDF
Responsible authority: Regional Assembly of Oulu Region
Applicant: City of Kuusamo
Total cost estimate 112 000 €
Requested ERDF and state funding 78 400 €

The aim of the project is to develop Kuusamo's business life so that its operations are based on the circular economy, low-carbon economy and resource wisdom.

It's a chunk! – European Capital of Culture boosts internationalisation of SMEs/ERDF
Responsible authority: Regional Assembly of Oulu Region
Applicant: Oulu Cultural Foundation sr
Sub-applicant: Oulu Tourism Ltd
Total cost estimate 253 420 €
ERDF and state funding requested 177 394 €

The project will increase the internationalisation of food and cultural tourism SMEs in the Northern Ostrobothnia region. The aim is to attract international tour operators or influencer visits to the region and to participate in international marketing networks related to food and cultural tourism.

Fatigue research environment for the development of highly demanding applications “FATE”/ERDF REACT-EU
Responsible authority: Regional Assembly of Oulu Region
Applicant: University of Oulu
Sub-applicant: Nivala Industrial Village Ltd
Total cost estimate 332 160 €
ERDF and state funding requested 232 512 €

The aim of the project is to support the specialisation of metal and engineering workshops in the production of low-carbon products in demanding conditions by enabling the expansion and internationalisation of fatigue research behind RDI operations.

Energy self-sufficient Kalajoki Marina as an accelerator of international tourism along the Arctic coast (Kalajoki Marina DMC) / ERDF REACT-EU
Responsible authority: Regional Assembly of Oulu Region
Applicant: City of Kalajoki
Total cost estimate 280 859 €
Requested ERDF and state funding 196 601 €

The main objective of the project is to support the internationalisation of tourism in Kalajoki.

PWR ON - Power to non-road machinery/ERDF
Responsible authority: Regional Assembly of Oulu Region
Applicant: Oulu University of Applied Sciences Ltd
Co-implementer: University of Oulu
Total cost estimate 952 858 €
Requested ERDF and state funding 667 000 €

In the project, NUVE-LAB's chassis dynamometer automation system will acquire a measurement interface for the machines being tested. In addition, the University of Oulu is developing a diagnostic system that expands the capabilities of the NUVE-LAB environment by providing testing capabilities related to machine maintenance and self-diagnostics.

COMO - Modernisation of the learning environment in mechanical engineering / ERDF
Responsible authority: Regional Assembly of Oulu Region
Applicant: Joint Municipal Authority for Education OSAO
Total cost estimate 291 700 €
Requested ERDF and state funding 204 190 €

The project provides companies with the opportunity to test the school's equipment base in the manufacture of their own products before possible own investments.

Improvement of wind energy transport routes in the Port of Raahe / ERDF
Applicant: Finnish Transport Infrastructure Agency
Funded by: North Ostrobothnia ELY
Total cost 755 160 €
Aid requested 377 580 €

Improving the connection between Highway 27 and Silatie in Haapajärvi / ERDF
Applicant: Finnish Transport Infrastructure Agency
Funded by: North Ostrobothnia ELY
Total cost 629 300 €
Aid requested 314 650 €

Highway 27 and the channelling of the Asematie junction and traffic lights, Nivala / ERDF
Applicant: Finnish Transport Infrastructure Agency
Funded by: North Ostrobothnia ELY
Total cost 1 069 810 €
Aid requested 534 905 €

Oulu2026 - Promoting diversity and strengthening the inclusion of minority groups in Northern Ostrobothnia and Kainuu / ESF+
Applicant: Oulu Cultural Foundation sr
Funded by: Northern Ostrobothnia Centre for Economic Development, Transport and the Environment
Total cost 461 376 €
Aid requested 369 100 € (the share of Northern Ostrobothnia is 221 460 €)

TUNTURI – Knowledge – and security skills as part of working life skills/ ESF
Applicant: Finnish Respiratory Association
Funded by: Northern Ostrobothnia Centre for Economic Development, Transport and the Environment
Total cost 206 760 €
Aid requested 165 408 €

GeroDigiLead/ESR
Applicant: University of Lapland
Co-implementers: Lapland University of Applied Sciences, University of Oulu
Funded by: Northern Ostrobothnia Centre for Economic Development, Transport and the Environment
Total cost 606 900 €
Aid requested 485 520 € (Nordic Ostrobothnia share 108 654 €)

GeroDigi/ESR
Applicant: Lapland University of Applied Sciences Ltd
Co-implementers: Oulu University of Applied Sciences Ltd, Centria University of Applied Sciences Ltd
Funded by: Northern Ostrobothnia Centre for Economic Development, Transport and the Environment
Total cost €641,727
Aid requested 513 381 € (Nordic Ostrobothnia share 146 700 €)

Rekryopo - Developing Recruitment Competence in Enterprises / ESF
Applicant: City of Kalajoki, City of Ylivieska
Funded by: Northern Ostrobothnia Centre for Economic Development, Transport and the Environment
Total cost 345 304 €
Aid requested 276 243 €

From workshops to working life / ESF
Applicant: Oulu Deaconess Institute Foundation sr
Funded by: Northern Ostrobothnia Centre for Economic Development, Transport and the Environment
Total cost € 815 661
Aid requested 652 528 €

Mark 2 / ESF
Applicant: Oulu Deaconess Institute Foundation sr
Funded by: Northern Ostrobothnia Centre for Economic Development, Transport and the Environment
Total cost 657 678 €
Aid requested 526 140 €

Of the flowers: cultural well-being and inclusion in suburbs and online / ESF
Applicant: Culture Power Station
Funded by: Northern Ostrobothnia Centre for Economic Development, Transport and the Environment
Total cost € 419 521
Aid requested 335 616 €

Hybrid producer 2026 / ESF+
Applicant: Oulu University of Applied Sciences Ltd
Co-implementer: Oulu Cultural Foundation sr
Funded by: Northern Ostrobothnia Centre for Economic Development, Transport and the Environment
Total cost 488 360 €
Aid requested 390 689 €

Ability to function and hope through social rehabilitation / ESF
Applicant: Caritas Foundation sr
Funded by: Northern Ostrobothnia Centre for Economic Development, Transport and the Environment
Total cost 541 533 €
Aid requested 433 227 €

Familiarise yourself with mental health – information and tools for mental health and nepsychology / ESF+
Applicant: Joint Municipal Authority for Education OSAO
Co-implementer: Oulu University of Applied Sciences Ltd
Funded by: Northern Ostrobothnia Centre for Economic Development, Transport and the Environment
Total cost 820 248 €
Aid requested 656 196 €

HYVVEE - Preparing companies in welfare sectors for change / ESF
Applicant: Nivala-Haapajärvi region NIHAK ry
Funded by: Northern Ostrobothnia Centre for Economic Development, Transport and the Environment
Total cost 99 880 €
Aid requested 79 904 €

PARTICIPATE - Skills needs for a changing world of work / ESF
Applicants: Nivala-Haapajärvi region NIHAK ry, the joint municipal authority of the Haapavesi-Siikalatva region
Funded by: Northern Ostrobothnia Centre for Economic Development, Transport and the Environment
Total cost 518 394 €
Aid requested 399 477 €

LUMI Natural, creative self - pathways to well-being / ESF
Applicants: KSAK Oy, Ksakki ry, Kuusamo College Supporting Association
Funded by: Northern Ostrobothnia Centre for Economic Development, Transport and the Environment
Total cost 568 405 €
Aid requested 426 299 €

Future leap – From second to future / ESF+
Applicants: Oulu University of Applied Sciences Ltd, University of Lapland, Kajaani University of Applied Sciences Ltd, University of Turku
Funded by: North Ostrobothnia Centre for Economic Development, Transport and the Environment
Total cost € 431 000
Aid requested 344 800 €
Northern Ostrobothnia share 159 435 € / 127 548 €

Next meeting

The next meeting of the secretariat of the Provincial Cooperation Group will be held on 31 January 2023.