TUULI - project

Sustainable wind power construction in Northern Ostrobothnia TUULI project

Read more about the completed materials of the TUULI project

Data from the location management model

Location management model report

Map material location management model's yes-, maybe- and no-areas and thematic maps of nature restrictions, landscape areas and cultural environments

Target cards Yes and Maybe Areas

Vision work report

Background studies

Green Structure and Ecosystem Service Survey

Linnusto's main migration route update report and species-specific maps

wolfrevir study

Eagle survey

Landscape survey report, landscape structure and landscape image maps (90 MB), Visibility area maps (109 MB) and landscape survey Target cards (115 MB). Due to the large size, it is advisable to store the data on your own computer after downloading to enable smooth reading. Please note: The target cards and map materials of the landscape survey have been updated on 11 December 2023.

It should be noted that some of the mitigation measures recorded in the destination cards of the TUULI project landscape survey are intended to guide more detailed project-specific planning on a wind turbine-specific level.

Electricity transmission report

Accessibility/Specialised transport route clearance

Alongside the TUULI project, a trafficability/special transport route survey has also been prepared for the areas of the wind turbines in the regional plans of North Ostrobothnia and Kainuu. The Ministry of the Environment's state subsidy for wind power construction has been received for the preparation of the report.

the Roadworthiness Report report

Presentation material and its attachments

Traffic accessibility study in North Ostrobothia and Kainuu

Annexes to the presentation

Background and objectives of the project

The TUULI project of the Regional Council of Northern Ostrobothnia was implemented between 1 June 2020 and 30 April 2023. The project has produced more new information on the suitability of the North Ostrobothnia region for wind power production and promoted sustainable wind power construction in the region. The aim of the project was to create conditions for the development of the wind power sector and thus for increasing emission-free electricity production in the North Ostrobothnia region, taking into account different aspects of sustainable development.

Sweco Finland Oy has acted as an expert consultant in the project, with Rejlers Finland Oy and William Velmala tmi as subcontractors. The eagle survey was prepared by Hannu Tikkanen from the Ostrobothnian environmental study Ay. The project is funded by the Centre for Economic Development, Transport and the Environment of Northern Ostrobothnia / European Regional Development Fund (ERDF), the member municipalities of Northern Ostrobothnia and the Regional Council of Northern Ostrobothnia. The total cost of the project is EUR 392 136.

The TUULI project consists of the following work packages:

  1. Establishment of strategic objectives for wind power generation and the siting of wind power (vision work)
  2. Areas suitable for wind power (location control model)
  3. Green Structure and Ecosystem Service Survey
  4. Linnusto's main migration route update report
  5. wolfrevir study
  6. Electricity transmission report
  7. Eagle survey
  8. Landscaping survey

As a result of the project, the wind power potential of Northern Ostrobothnia and a provincial view of the most suitable areas for wind power construction can be presented. The aim is to form a regional wind power development picture and to achieve a commitment to realising the provincial vision.

Regional plan for the energy and climate phase of Northern Ostrobothnia

The regional plan for the energy and climate phase discusses, for example, the region's wind power system, the assignment of new wind power areas, the development needs of electricity transmission, the regional structure, the transport system, the ecological network and climate impact assessment.

The regional plan for the energy and climate phase was approved at the meeting of the provincial council on 27 May 2025 and entered into force without legal force by decision of the provincial government on 18 August 2025.

The results and background studies of the TUULI project have been an important part of the renewal of the regional plan. During the proposal phase of the provincial plan, in spring 2024, the following actions were carried out: Report on Natura sites and ecological network, which examined the impacts of wind power construction on Natura sites in Northern Ostrobothnia and the ecological network of protected areas outside Natura sites.

The regional plan for the energy and climate phase of Northern Ostrobothnia identifies 50 new regional wind turbine areas, including 45 TV-1 areas for land and 5 TV-2 areas for the sea. A site description has been drawn up for each area of wind turbines in the regional energy and climate plan, and these must be used in more detailed planning instead of the TUULI project site cards drawn up during the preparation phase of the regional energy and climate plan. The regional plan data for the energy and climate phase, including the target descriptions, can be found in: the Regional Planning Website. In the planning of wind power projects, the reports drawn up in the regional energy and climate phase planning process and in the TUULI project must be used.

In the draft and proposal phases of the energy and climate phase regional plan, the planning situation of the TV areas designated in the final phase 1 and 3 regional plans and the suitability of the TV areas for the wind power construction objectives of the energy and climate phase regional plan were also examined. Of the legally valid phase 1 and phase 3 regional plans, 48 TV-1 areas remain, all of which are located on land. In total, 98 regional wind turbine areas (TV-1 and TV-2) are designated in the phase region plans for Northern Ostrobothnia.

The definition of the area of regionally significant wind power plants was restored in the public proposal phase of the energy and climate phase regional plan (in 2024) to comply with the legally valid phase 1 and 3 regional plans, i.e. the regionally significant entity is a ten (10) or more wind power project.

Previous wind power surveys and wind power regional plans

the North Ostrobothnia a regional wind power survey was drawn up in 2010-2011;. The wind power sector and wind power technology have developed strongly over the last ten years, which made a new overall study necessary. Three regional plans enabling and guiding wind power construction have been drawn up in Northern Ostrobothnia:

Read the story map of the TUULI project

the Story Map You can learn more about the situational picture of wind power construction in the region and the contents of the work packages of the TUULI project. NB! story map has not been updated for wind power projects since 2023.

Presentations related to the situational picture of the TUULI project and wind power construction

the TUULI Project Final Seminar The presentation material can be downloaded here 29.9.2022.

North Ostrobothnia Villages and Village Associations info session 2.6.2022 (Teams). Get to know Introductory material for the village evening.

Presentation at the Regional Parliament on 2 November 2021: North Ostrobothnia will continue to be a wind power region in the future

Press releases

Press release published on 7 December 2020

Press release published on 17 June 2022

Further information:

Erika Kylmänen, Environmental Manager, tel. 040 685 4041

Sari Pulkka, Regional Planning Specialist, tel. 040 685 4037

firstname.lastname(at)pohjois-pohjanmaa.fi